Drawing dependencies between tasks
To draw dependencies between tasks:
- Open 10-3 Schedules.
- Using the data control, select an existing schedule and click the Grid/Gantt button.
- On the Mode menu, click Draw Predecessors.
- Click the start or finish of a task, and then drag to the start or finish of another task.
Tip:
- Connect a task to a predecessor, moving from the bottom to the top of the Gantt chart.
- You can assign task dependencies between jobs.