Drawing dependencies between tasks

To draw dependencies between tasks:

  1. Open 10-3 Schedules.
  2. Using the data control, select an existing schedule and click the Grid/Gantt button.
  3. On the Mode menu, click Draw Predecessors.
  4. Click the start or finish of a task, and then drag to the start or finish of another task.

Tip:

  • Connect a task to a predecessor, moving from the bottom to the top of the Gantt chart.
  • You can assign task dependencies between jobs.