Viewing the critical path in schedules

You can view the path of all the critical tasks in your schedule.

To view the critical path in a schedule:

  1. Open 10-3 Schedules.

  2. Using the data control, select an existing schedule.

  3. On the Options menu, select Grid/Gantt Chart.

    The window appears with a Gantt chart in the right-hand pane.

  4. From the checkboxes above the chart, select Critical Path.

    The non-critical tasks appear shaded light gray in the chart.