You can view the path of all the critical tasks in your schedule.
Open 10-3 Schedules.
Using the data control, select an existing schedule.
On the Options menu, select Grid/Gantt Chart.
The window appears with a Gantt chart in the right-hand pane.
From the check boxes above the chart, select Critical Path.
The non-critical tasks appear shaded light gray in the chart.