Working with 6-Project Management > 6-2 Budgets > Creating budgets
Learn more

About displaying budget recaps

Entering the settings for Cost Over Budget Warning

About exporting files from 6-2 Budgets and 6-9 Proposals and 6-10 Unitary Proposals

How change orders affect budgets and proposals and subcontracts

Exporting budgets from 9-5 Takeoffs to 6-2 Budgets

Creating budgets

Typically, you create a job before creating a budget. You can create new jobs in 3-5 Jobs (Accounts Receivable).

Important! To match historical job costs with a budget, you must enter them both using the same method.

Consider the following points before creating a budget:

Important! Only four of the buttons in the data control activate areas in 6-2 Budgets: First, Previous, Next, and Last. The Display Lookup drop-down arrow displays the Accounts Receivable Lookup window, and the detail button displays the 3-5 Jobs (Accounts Receivable) window.

To create a budget:

  1. Open 6-2 Budgets.
  2. Using the data control, select a specific job.
  3. In the Phase list, click the phase for which you want to create a budget.
  4. To populate the budget grid with cost code values, do one of the following:

    • To import cost codes from a Lookup window, right-click the cell and click Display Lookup Window, or click the drop-down arrow. Then double-click each item to import it into the budget.
    • To import cost codes from a Picklist window, right-click the cell and click Display Pick List Window. Then double-click the items that you want to import into the budget. Next, click the Insert Selected Items button to import all the selected items into the budget.
    • To import a *.budget_grid file, click Options, point to Import, then click Grid File. Browse to the appropriate file, then double-click it.
  5. In the grid, for each cost code:

    1. In the Hours cell, enter the estimated hours if the cost code has associated labor costs.
    2. In the Material cell, enter the material costs.
    3. In the Labor cell, enter the labor costs.
    4. In the Equipment cell, enter the equipment costs.
    5. In the Subcontract cell, enter the subcontract costs.
    6. In the Other cell, enter the miscellaneous costs.
  6. On the File menu, click Save.

Note: If you exported the budget from Takeoffs, Sage 100 Contractor inserts the data from the takeoff.