Assigning equipment resources

To assign equipment resources:

  1. Open 10-3 Schedules. In the data control box, enter the job number.
  2. In the Phase list, click the phase.
  3. In the Task# column, select the task(s) to which you want to assign equipment.
  4. On the Options menu, click Equipment.
  5. In the Equipment cell, do one of the following:

    • Enter the equipment number.
    • Right-click the cell to open the Lookup window, then select the equipment.
  6. In the Start Time cell, enter the time you expect the equipment to begin.
  7. In the End Time cell, enter the time you expect the equipment to finish.
  8. Repeat steps 5–7 for each piece of equipment you want to assign to the task.
  9. Click File > Save.