Assigning equipment resources
To assign equipment resources:
- Open 10-3 Schedules. In the data control box, enter the job number.
- In the Phase list, click the phase.
- In the Task# column, select the task(s) to which you want to assign equipment.
- On the Options menu, click Equipment.
-
In the Equipment cell, do one of the following:
- Enter the equipment number.
- Right-click the cell to open the Lookup window, then select the equipment.
- In the Start Time cell, enter the time you expect the equipment to begin.
- In the End Time cell, enter the time you expect the equipment to finish.
- Repeat steps 5–7 for each piece of equipment you want to assign to the task.
- Click > .