About displaying budget recaps
Enabling the Over Budget Warning
About exporting files from 6-2 Budgets and 6-9 Proposals and 6-10 Unitary Proposals
How change orders affect budgets and proposals and subcontracts
Displaying and printing budget cost code or phases recaps
- 
                                                    
Open 6-2 Budgets.
 - 
                                                    
Using the data control, locate a job.
 - 
                                                    
From the Options menu, select Recap and one of the following:
- Cost Codes
 - Phases
 
 - 
                                                    
On the Budget Recap window, click the Print records button.
 - 
                                                    